News: Kung Oscars väg

Kung Oscars väg April 30, 2008 - 25 metres down

 

Next to nothing is visible in Slottsparken at Kung Oscars väg today. A small hut that will soon be replaced by a hatch in the ground is all that remains of the construction site that has been there for some time. Restoring groundwork has been in progress for a while and is almost finished, but there are activities under ground. The picture shows the stairs that have been cast all the way from ground level in the park and they will end in cross passage 3 between the two tunnels. This is one of the rescue service access points in case of a future accident in the tunnel.

 

Photo: Pia Sjöholm


Kung Oscars väg April 18, 2008

 


February 5, 2008


December 18, 2007

In December the days are short, so now we better turn the lights on. The casting works in Kung Oscars väg are finished and soon the backfilling and restoration works will begin.


September 26, 2007


July 16, 2007





In Kung Oscars väg in Slottsparken the casting continues and currently slightly more than 10 meters out of a total of 25 meters have been cast. Simultaneously with the casting in the shaft, stairs are cast next to the shaft.


June 26, 2007

 


May 31, 2007


April 30, 2007

Rock excavation works are ongoing and now – the second week of May – we have reached 23 metres down and in about two weeks time we will have reached the bottom. After that we will carry out the same works that was done in the other rescue shaft at Stadiongatan previously.

2007-03-30

Preparation for rock excavation in shaft.

2007-03-01

Kung Oscars väg January 23, 2007

Excavation at Kung Oscars väg is ongoing and in the beginning of March the limestone will be reached.



Photo: Keith Edmonds

September 21, 2006

October 31, 2006

2006-09-21 2006-10-31